Whether to repair or replace a deck comes down to one question: is the frame still good? Boards and rail can be renewed. The ledger, posts, footings and joists hold you up. Here is how to check each one yourself, and what the permit rules around Omaha say about each fix.
A deck with tired boards on a sound frame is a candidate for new decking and rail. A deck with fresh boards on a rotted ledger is not safe at any age. So the check starts where the deck meets the house and ends at the boards, the opposite of the order most people look in. You need a flashlight and a screwdriver. Sound wood resists the tip. Rotting wood lets it sink in, and feels soft or spongy.
The ledger is the board fastened to the house that carries one whole side of the deck. Look at it from underneath. You want to see bolts or lag screws rather than nails alone, a metal hanger holding each joist, and flashing that keeps water out of the joint. Omaha's deck guidelines tell builders to take extreme care here: the ledger has to be bolted into solid, structurally sound material, and a deck may not hang from a house cantilever or from masonry veneer. La Vista requires flashing between the deck and the house and galvanized joist hangers at the ledger. Dark streaks, rust trails below the hardware, a gap opening between the ledger and the house, or soft wood in the ledger itself are the most serious findings on this list.
For a deck attached to the house, Omaha, Gretna and La Vista all put the bottom of the footings 42 inches below grade, under the frost line. A footing that is too shallow lifts and settles with every winter. You cannot see the depth, but you can see the result: posts that lean, a deck that has pulled out of level, or stairs that no longer meet their landing. Check the base of each post as well, because wood that stays wet at ground level rots there first. Omaha requires each post to be anchored to its footing with an approved fastener, and La Vista calls for posts that rest on top of the footing on a one-inch standoff.
Joists tend to rot from the top, under the seams between boards, where water sits and old fasteners have opened the grain. Push the screwdriver into the top edge of several joists from below, and look at the hangers and hardware for heavy rust. A beam that sags between posts, or a joist that has split at its hanger, is a structural problem. One or two bad joists can sometimes be replaced. Soft spots along many of them mean the frame is done.
Stringers are the notched boards that carry the treads, and they are often among the first structural parts to rot: the bottom ends sit at or near the ground, and every notch exposes end grain to the weather. Check the bottom of each stringer and the notches for soft wood, then stand on the stairs. They should not sway, bounce or pull away from the deck. A rotting deck stair stringer gets replaced, not patched. While you are there, measure a few steps. Gretna and La Vista cap each riser at 7 3/4 inches and want treads at least 10 inches deep, with no more than 3/8 inch of difference from one step to the next. Old stairs that have settled often fail that last test.
Lean on the rail, firmly, everywhere a person might. It should not move. Omaha requires a guardrail at least 36 inches high around any deck more than 30 inches above the ground, with no opening a 4-inch ball could pass through, and a graspable handrail 34 to 38 inches above the tread nosings on any stairway with more than three risers. Many older decks miss one of those. A loose rail on a high deck is a reason to stay off the deck until it is fixed.
Now the part everyone starts with. Rotting deck boards show up first at the board ends, around fasteners and wherever leaves or planters keep the wood wet. A few soft boards on a sound frame is the easy case: those boards are replaced, and the joist under each one is checked while it is exposed. Boards that are cracked, cupped and soft across the whole deck usually mean the frame deserves the same hard look.
If the ledger is solid and flashed, the posts are plumb, the joists are firm along their tops and the stairs do not move, the structure has life left. New decking and a new rail on that frame can give an old deck years more. One caution if you are thinking of switching to composite: composite boards come with their own span tables, often tighter than an old wood deck was framed for, and Omaha's deck guidelines require any product with a manufacturer's installation manual to be installed the way the manual says. The frame has to suit the new boards. The composite vs. wood guide covers that choice.
At that point new boards go onto a frame that will not outlast them. A replacement starts with new footings and ends with a deck that has been inspected along the way.
Omaha requires a permit for every new deck and every deck replacement. Repairs need one too when they involve the handrails, guardrails, floor joists, beams, posts or footings. Swapping deck boards is not on that list; ask the permit office if you are not sure where your repair falls. A permitted deck in Omaha gets a footing inspection, a framing inspection and a final. Gretna requires a permit to build or add to a deck and for repairs to structural components, and inspects the footing holes before the concrete is poured. The building permits guide has the drawings and setbacks each city asks for.
It depends far more on how the deck was built and kept than on its age. Footings below the frost line, a flashed ledger, hardware rated for treated lumber and boards that are cleaned and sealed on a regular schedule all stretch it. Omaha requires all lumber exposed to the weather to be pressure-treated or naturally durable, and Gretna says the same for any wood that touches the ground or concrete or sits within 18 inches of the ground. A deck built without those details, or left bare to the sun for years, wears out much sooner. That is why the check above tells you more than the year the deck was built.
We build new decks and replace old ones around Omaha and Gretna, and the deck builders page shows finished work. If your check turned up anything on the replacement list, or you are not sure what you are looking at, send a few photos of the deck, including the underside, and Chris will get back to you within a business day. A roof over the new deck is its own decision, and the covered porch page covers it.
Checked against these official pages on November 16, 2026. Rules change, and your permit office has the last word.
Owner-run since 1995. Chris Cannon bids the job, runs the job and answers the phone. One crew, one point of contact, no surprises.
Real jobs from around the Omaha metro. Tap any photo to open it.
Check the frame, not the boards. If the ledger is solid and flashed, the posts are plumb, the joists are firm and the stairs do not move, new boards and rail can be enough. If the ledger or joists are rotted, the posts sit on shallow footings or the stairs move, it is a replacement.
If the frame under them is sound, yes: the soft boards are replaced and the joist under each one is checked while it is exposed. If boards are failing across the whole deck, look hard at the joists, the ledger and the posts before putting new decking on an old frame.
Replace it. Stringers carry the stairs, and rot usually starts at the bottom ends and in the notches. Gretna and La Vista want risers no taller than 7 3/4 inches and treads at least 10 inches deep, and Omaha requires a graspable handrail on any stairway with more than three risers.
In Omaha, yes: every new deck and every deck replacement needs a permit, with a plot plan, a cross section and a footing layout. Gretna and La Vista require deck permits too.
For repairs that involve the handrails, guardrails, floor joists, beams, posts or footings, yes. Replacing deck boards is not on the city's list. Gretna requires a permit for repairs to structural components.
It depends more on how it was built and kept than on the calendar. Footings below the frost line, a flashed ledger and boards that are cleaned and sealed regularly all stretch it. When a wood deck fails, it is usually the frame or the ledger, not the boards, that makes it a rebuild.
Only if the frame is sound and matches the composite maker's span tables, which are often tighter than an old wood deck was framed for. Omaha's deck guidelines require any product with a manufacturer's installation manual to be installed the way the manual says.
Lean on the rails, stand on the stairs and look underneath. Rails and stairs should not move, posts should be plumb, and the board against the house should be bolted, flashed and free of rot. If any of that fails, stay off the deck until it has been looked at.
Tell us what you're thinking and where the house is. Chris will get back to you within a business day.