Most remodeling around Omaha needs a building permit: basement finishes, decks, additions and porch roofs always, kitchens and baths in most cities. Here are the Omaha building permit requirements job by job, and how Gretna, Papillion, La Vista, Bellevue and Sarpy County differ, checked against each city's own rules.
City limits decide it, not your mailing address. A Gretna, Papillion or Elkhorn address can belong to an acreage outside the city, and each city also controls a zone around its limits. Here is how the metro splits up:
The codes differ a little too. Omaha and Douglas County work from the 2018 International Residential Code with Omaha's amendments, La Vista from the 2018 codes, and Gretna from the 2021 edition. For most remodels the differences are small. The ones that matter are below.
A basement finish is permit work in Omaha, Gretna, Papillion and Bellevue, and Springfield lists basement finishes on its permit list as well. The building permit covers the framing; electrical and plumbing permits ride alongside it. Expect the city to see the work in stages. Gretna's basement guideline lists six inspections: the plumbing under the slab, the electrical rough-in, the framing rough-in (framing, ductwork and plumbing), the insulation, the final electrical and the final building inspection.
The bedroom rules ride with the permit. Any new basement bedroom needs an egress window or a door to the outside, and in Omaha any room over 70 square feet with a built-in closet counts as a bedroom for that rule. The basement egress guide has the window rules, and the basement checklist covers the rest of what to settle first.
In Omaha, yes. The city's deck guidelines require a permit for every new deck and every deck replacement, and for repairs that involve the handrails, guardrails, joists, beams, posts or footings. Gretna, La Vista and Papillion require deck permits as well. The application wants a site plan with the distances to your lot lines; Omaha also asks for a cross section from the footings to the house and a footing layout.
What the inspector checks is consistent across the metro:
Replacing only the deck boards is not on Omaha's list; anything structural is. If the frame, ledger or footings are tired, it is a rebuild, and a rebuild needs the permit either way. The deck builders page and the composite vs. wood guide cover the build itself.
A roof is a structure, so it is permit work. Omaha lists a deck or patio cover and a pergola as their own permit types, both with drawings. Gretna requires a permit for a porch, a patio cover or enclosing a deck, and La Vista's accessory permit covers patio covers. The roof has to carry snow (Douglas County's design data puts the ground snow load at 25 pounds per square foot), and its posts need footings below the frost line like the rest of the house. The home additions page and the covered porches page show what we build.
This is where the cities differ most. Gretna requires a permit to remodel a kitchen or a bathroom, but not to swap cabinets, countertops or a sink in the same spot, or to lay new flooring. Omaha lists kitchen remodels and bath remodels as their own permit types. Inside the house, Bellevue's exemptions stop at painting, papering, floor covering and similar cosmetic work. In every city we checked, new wiring and moved plumbing bring their own electrical and plumbing permits, whatever the building permit says.
So do you need a permit for a bathroom renovation? If anything behind the wall moves (a drain, a valve, a fan circuit, a wall), plan on yes. A new vanity top on the same plumbing does not need one in Gretna. The bathroom remodeling and kitchen remodeling pages show the work, and the guide to converting a tub to a walk-in shower covers the plumbing rules for that job.
Always. An addition has footings, a foundation, framing, a roof and usually every trade, every city we checked lists it as permit work, and Omaha requires drawings with the application. The drawings show the setbacks from your lot lines, so the lot decides part of the addition's size before anyone draws a room. Footings go to the frost line: 42 inches in Omaha and Douglas County.
Gretna does not require a permit for house siding, for re-shingling that does not touch the rafters or replace more than one sheet of roof decking (its rule adds that ice shield must be installed), or for windows and doors that fit the existing openings. Omaha is the opposite: re-roofs, roof repairs, re-siding and window replacement are all residential permit types. La Vista covers roofs, siding and windows with its accessory and light remodeling permit, and Bellevue's exemption list does not include them. A new or bigger window or door opening needs a permit in every city we checked. The siding, roof replacement and repair and window replacement pages cover the work itself.
Gretna and Bellevue both publish lists. Between them: painting, wallpaper and similar finish work, floor covering, a retaining wall up to 4 feet measured from the bottom of the footing, a small shed (Bellevue: one story, up to 120 square feet), and swapping a water heater, furnace or air conditioner on the same power source (Gretna). Anything bigger, ask before you assume; a moved wall or a new circuit brings a permit in every city we checked.
In Omaha, starting construction before the permit is issued costs four times the regular permit fee. In Gretna a permit expires if the work has not substantially started within 180 days, or is not finished within a year. Work done without a permit can also come up when you sell, when a buyer's inspector asks what was done and whether it was inspected.
A homeowner can pull some permits. Gretna's basement guideline lets an owner who lives in the house do their own basement plumbing and wiring, and Omaha has homeowners apply for electrical permits in person at the office. When a contractor does the work, settle in writing who pulls the permit and who schedules the inspections. On our jobs that is us: Callaway Construction Inc. pulls the permit, and the inspections go on the schedule from the first day.
If the job touches structure, plumbing, wiring or the outside of the house, the permit is part of the job, and so is the order the inspections come in. Tell us about the project and where the house is, and Chris will tell you at the walkthrough what your job needs and who issues it.
Checked against these official pages on November 12, 2026. Rules change, and your permit office has the last word.
Owner-run since 1995. Chris Cannon bids the job, runs the job and answers the phone. One crew, one point of contact, no surprises.
Basement finishes, decks and deck replacements, additions, deck and patio covers, egress windows, and kitchen and bath remodels, which Omaha lists as their own residential permit types, along with re-roofs, re-siding and window replacement. Electrical and plumbing work need their own permits.
Yes. Omaha treats a basement finish as permit work, and so do Gretna, Papillion and Bellevue, with electrical and plumbing permits alongside the building permit. Any new bedroom needs an egress window, and in Omaha a room over 70 square feet with a built-in closet counts as a bedroom.
In Omaha, yes: every new deck and every deck replacement needs one, and so do repairs to the rails, joists, beams, posts or footings. Gretna, La Vista and Papillion require deck permits too. Attached decks need footings 42 inches below grade.
Usually. Gretna requires one to remodel a bathroom, Omaha lists bath remodels as a permit type, and moving a drain or adding a circuit brings plumbing or electrical permits. In Gretna, a new countertop or sink on the same plumbing, or new flooring, does not need one.
Yes. Omaha lists deck and patio covers as their own permit type, with drawings, and a porch roof is built for snow load with its posts on frost-depth footings. Gretna and La Vista require a permit for patio covers too.
It depends on the city. Omaha lists re-roofs, roof repairs, re-siding and window replacement as permit types, and La Vista covers them with its accessory permit. Gretna does not require a permit for siding, ordinary re-shingling or windows that fit the existing openings.
Sarpy County Planning and Building, if the property is outside the city limits and outside the city's zone around them; inside that zone, the city still issues it. In rural western Douglas County, Bennington and Waterloo, it is Douglas County Permits and Inspections.
The permit fee becomes four times the regular fee. Gretna permits also expire if the work has not substantially started within 180 days, or is not finished within a year.
Yes, for any job in Nebraska that needs one, and the inspections go into the schedule. For Council Bluffs, ask Chris at the walkthrough.
Tell us what you're thinking and where the house is. Chris will get back to you within a business day.